What is the primary consideration when ordering steel for erection on-site?

Study for the Construction Estimating 2 Exam. Dive into flashcards, multiple choice questions, and comprehensive explanations. Equip yourself for success!

The primary consideration when ordering steel for erection on-site revolves around how it will be erected and the forms needed by phase of erection. This focus ensures that the delivery and scheduling of materials align perfectly with the construction progress, allowing for an efficient workflow on-site.

Understanding the erection sequence is crucial for several reasons. It determines the structural integrity of the assembly, impacts the safety protocols that need to be in place, and affects the overall schedule of the project. Accurate planning for erection phases ensures that the correct sizes and shapes of steel structures are delivered at the appropriate times, avoiding delays or the need for reworking.

While factors like the type of steel, cost of transportation, and availability of labor are significant, they are secondary to the detailed logistics and coordination involved in the actual erection process. Focusing on how the steel will be erected allows project managers and estimators to anticipate potential challenges and prepare effectively, ensuring that the project stays on track and within its budget.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy