How is concrete typically priced once it has been taken off?

Study for the Construction Estimating 2 Exam. Dive into flashcards, multiple choice questions, and comprehensive explanations. Equip yourself for success!

Concrete is typically priced by cubic yard because this method accurately reflects the volume of the material needed for a construction project. Since concrete is a volumetric material, measuring it in cubic yards allows estimators to consider both the depth and area that will require concrete. This unit of measurement is standard in the industry, providing clarity and consistency in pricing, particularly for large-scale projects where precise material quantities are essential for budget planning and resource allocation.

Calculating costs using cubic yards ensures that all elements of the pour, whether for foundations, slabs, or additional concrete features, are accounted for based on their volume, making it a reliable choice for estimating. This approach aligns well with how concrete is delivered and measured by suppliers, further simplifying ordering processes and ensuring that the contractor receives the accurate amount needed to complete the work.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy